Next stage of diagnostics of Power of Siberia gas pipeline

In November 2021 LLC NPC VTD finished technical diagnostics of next section of Power of Siberia gas pipeline from Chayandinskoye field to transboundary section with China via Amur River.

Total length of inspected sections was more than 2,170 km.

Despite the difficult transport accessibility, harsh climatic conditions, wall thickness up to 32 mm and length of some sections up to 300 km, works were finished at considerable advance rate in full compliance with the customer's technical requirements.